Ordering precast glass block flooring

Precast is always produced to order and not available as a stock item. Before being cast production drawings must be checked and signed off. It is imperative to allow lead time for curing and production.

Allow a minimum of between four and six weeks, excluding holiday periods, dependent on the number of panels required.

Working with Glass Block Technology and procurement of precast floor panels

When designs or feasibility outlines are submitted, recommendations and suggestions can be discussed. The next step is to then produce a costing estimate and general arrangement or production drawings. This should outline block, paver or lens reference, panel length, width and thickness dimensions, joint and border widths, panel weight and lifting socket position.

Fire rating and loading requirements should have also been confirmed at discussion stage, prior to estimate or production drawings or orders being placed.